How the volume is worked out
A strip footing is a long rectangular block. Multiply its length by its width and depth, with those two converted to feet.
Cubic yards = length × (width ÷ 12) × (depth ÷ 12) ÷ 27
A worked example
One hundred feet of footing 20 inches wide and 10 inches deep is 138.9 cubic feet. With 10% extra that is 152.8 cubic feet, or 5.66 cubic yards. That is a ready-mix order. In bags it would be 255 of the 80 lb size.
Good to know
- Footing width and depth are set by the building code, based on the soil and the load. A common rule for houses is a footing twice as wide as the wall it carries, but check your code or plans.
- The bottom of the footing must sit below the frost line for your area.
- Footings poured straight into a trench use more concrete than the drawings suggest, because the sides are rough. Ten percent extra is a sensible minimum.
- For the rebar, see the rebar calculator.
Common questions
What about round pier footings?
Use the post hole concrete calculator, which works out cylinders.
Should I order ready-mix or use bags?
Anything over about a cubic yard is easier and usually cheaper from a truck. Footings should be poured in one go where possible.
How we know this calculator is right
Before this calculator went on the site, 6 answers were worked out separately from its code, by hand or straight from the formula above. Each time this page loads, your own browser runs the calculator on those same numbers and compares. Turn on JavaScript to see the comparison.
See every check
| Numbers used | Result | Worked out separately | This calculator |
|---|
What this proves: the calculator does the arithmetic of the formula shown, correctly. What it cannot prove: your measurements, or figures such as coverage per bag, waste and spacing, which are typical starting values you can change. Go by the product label and your local code.