How it is worked out
Earned to date = contract amount × percent complete
Amount due = earned − retainage − already billed
A worked example
On a $50,000 contract that is 40% complete, $20,000 has been earned. With 10% retainage, $2,000 is held back. If $9,000 was billed on an earlier invoice, this one is for $9,000.
Good to know
- The retainage is still owed to you. It is billed separately at the end, usually after the punch list is done.
- On larger jobs the percent complete is worked out line by line on a schedule of values, not as one figure for the whole job.
- Add approved change orders to the contract amount before you work out the percentage.
- Many states limit how much retainage can be held and how quickly it must be released. Check the rules where you work.
Common questions
Should I bill for materials on site but not installed?
Only if your contract allows stored materials to be billed. If it does, list them separately on the invoice.
How we know this calculator is right
Before this calculator went on the site, 9 answers were worked out separately from its code, by hand or straight from the formula above. Each time this page loads, your own browser runs the calculator on those same numbers and compares. Turn on JavaScript to see the comparison.
See every check
| Numbers used | Result | Worked out separately | This calculator |
|---|
What this proves: the calculator does the arithmetic of the formula shown, correctly. What it cannot prove: your measurements, or figures such as coverage per bag, waste and spacing, which are typical starting values you can change. Go by the product label and your local code.