How the fall is worked out
Multiply the length of the run by the slope per foot.
Total fall = pipe run × slope per foot
A worked example
A drain 40 feet long at a quarter inch per foot drops 10 inches from start to finish. That is a 2.08% grade, or 2½ inches every 10 feet.
Good to know
- Plumbing codes commonly require at least a quarter inch per foot for pipes up to about 3 inches, and allow an eighth of an inch per foot for larger ones. Check the code in force where you are.
- Too little slope lets solids settle. Too much can let the water run ahead and leave solids behind. Aim for the specified slope, not the steepest you can fit.
- Work out the fall before you dig or drill, to make sure the far end still sits above the sewer or septic connection.
- Support the pipe evenly so it does not sag between hangers. A belly in the line holds water.
Common questions
How do I set the slope on site?
On a 4 foot level, a quarter inch per foot is a 1 inch gap under the low end. Many levels also have a vial marked for it.
Is this the same for a French drain or yard drain?
Yard drains can run flatter. One percent, about an eighth of an inch per foot, is a common minimum.
How we know this calculator is right
Before this calculator went on the site, 8 answers were worked out separately from its code, by hand or straight from the formula above. Each time this page loads, your own browser runs the calculator on those same numbers and compares. Turn on JavaScript to see the comparison.
See every check
| Numbers used | Result | Worked out separately | This calculator |
|---|
What this proves: the calculator does the arithmetic of the formula shown, correctly. What it cannot prove: your measurements, or figures such as coverage per bag, waste and spacing, which are typical starting values you can change. Go by the product label and your local code.