Every Single CalculatorOne place for every calculator
ΩPlumbing, HVAC and electrical

Conduit stub-up calculator

Enter how tall the stub needs to be and the size of the conduit to find where to make your mark.

Example: You need a 12 inch stub into a box in half inch EMT and want the mark in the right place first time.

Your numbers

A hand bender adds a fixed amount to the stub as it forms the bend. That amount is the take-up, and you subtract it from the height you want.

in
Floor to the end of the conduit.
  • Mark the conduit at0
  • Take-up for this size0
  • Finished stub height0

How the mark is worked out

Mark = stub-up height − take-up

The standard take-up figures for hand benders are 5 inches for ½ inch EMT, 6 inches for ¾ inch, 8 inches for 1 inch and 11 inches for 1¼ inch.

A worked example

For a 12 inch stub in ½ inch EMT, measure 7 inches from the end of the conduit and mark it. Line that mark up with the arrow on the bender, with the hook facing the end you measured from, and bend to 90 degrees. The stub comes out 12 inches tall.

Good to know

  • The take-up is stamped on most benders. If yours differs from the figures here, use the one on the tool.
  • Keep firm foot pressure on the bender heel through the whole bend, or the conduit kinks.
  • Check the stub with a level and a tape before you cut the other end. A bend can be opened or closed a little while it is still in the bender.
  • Rigid and IMC use different benders and different take-up figures.

Common questions

What about an offset or a kick?

The conduit offset calculator gives the spacing between bends and the shrink.

How we know this calculator is right

Before this calculator went on the site, 6 answers were worked out separately from its code, by hand or straight from the formula above. Each time this page loads, your own browser runs the calculator on those same numbers and compares. Turn on JavaScript to see the comparison.

See every check
Numbers usedResultWorked out separatelyThis calculator

What this proves: the calculator does the arithmetic of the formula shown, correctly. What it cannot prove: your measurements, or figures such as coverage per bag, waste and spacing, which are typical starting values you can change. Go by the product label and your local code.

Used by: electricians.